Nail the cut off shingle into place about 6 inches from its lower edge.
How high to start first course of siding.
Hammer in one nail about 2 inches from each end of each shingle and another nail about 1 inch above each cutout.
Spend the extra few bucks on the wider stuff and start your siding a bit lower.
Use a table saw to rip a 1 wide strip of the siding.
Generally a starter piece is installed underneath the first course to simulate the typical overlap and to orient the panel at the proper angle.
The walls should be stripped of all previous siding and the surface should be fairly smooth and flat because lap siding will follow along any contours.
Add approximately 1 4 6 4mm to both sides to allow for expansion and contraction of the siding.
This is where the new siding will begin.
Preparing walls for lap siding.
This will be used as a template for the horizontal cuts.
These marks represent the vertical cuts fig.
This project is using an 8 wide siding with a 1 overlap resulting in a 7 reveal.
The method discussed here is an easier and more common one installing corner trim first and then butting the siding to it.
Vinyl siding starter strips snap a level chalk line for the first starter strip at the base of the wall no less than 8 inches above ground level after determining the lowest corner of the house.
To provide a common reference point measure up 8 in.
Begin by installing the first row of siding on both sides of the deck.
From the top of this row and stretch a string line across the deck.
Make sure to keep nails out of the tar strip as you work.
This chalk line should be level and a consistent distance from the eaves or the top and bottom of the windows.
Once you ve decided where you want the siding to begin drive a nail through a point on your chosen starting height and snap a chalk line around the perimeter of the house.
Click here to learn some vinyl siding cleaning techniques that will make your house look new.